We are using clarity 7.5. We have a project with start date 03/08/15 and end date 31/01/18. In that project currently budgeted cost start date is showing as 03/08/15 and Budgeted Cost Finish as 26/02/16. We would like change the budgeted finish date to project end date that is 31/01/18. But whenever we are change the Budgeted Cost Finish the budgeted cost start is getting changed automatically. It looks like we can change the dates but cant extend the duration.
Could you please let me know if there is any way to do it.
Please find the attached screenshot for your reference.
Thanks,