Weighted Completion Percentage based on size estimate?

Question asked by Misetic on Oct 30, 2017
Latest reply on Nov 5, 2017 by Misetic

Is there a functionality to where the refined estimate for each user story can generate a weighted completion percentage for the parent feature? Currently, each feature has user stories with different preliminary size estimate from XS to XL.  But we would like to input a refined estimate for each story after the start of the iteration which will then be compiled into a weighted in-progress completion percentage for the parent feature.

 

Currently if five SMALL stories are complete and five LARGE stories are not complete, it will display a 50% in-progress completion percentage for the parent feature, when in reality the real world weighted completion percentage is more like 20%.

 

Tracking completion percentage by feature is very important for our program management. Any help would be appreciated.

 

Any ideas on if this is possible?