Clarity

  • 1.  Recurring Tasks

    Posted Nov 15, 2017 11:15 AM

    Does anyone know of a way to setup recurring tasks in the PPM Gantt Chart?



  • 2.  Re: Recurring Tasks

    Posted Nov 15, 2017 02:15 PM

    A way to do that is to 

    create the task(s)

    assign resource(s)

    set ETC on the reoccurring dates

    set the loading pattern to fixed

    CA PPM does not have reoccuring tasks like MS Project