Hello,
I have a question related to unfinished work for split stories. When splitting a story, if there are unfinished tasks they are carried over to the [Continued] story on the new sprint. These tasks have estimate, ToDo and Actuals.
What is the guidelines on what to do with these values at the beginning of the new sprint?
It seems to me, the Estimate should be updated based on the ToDo.
The ToDo field would have the same value as the Estimate.
The Actual field should be blank.
Does it make sense?
Thanks!
Claudia