Clarity

  • 1.  Rate Matrix - Industry Best Practice

    Posted Dec 26, 2017 03:17 AM

    CA-PPM Version : 14.3

     

    Can someone share the industry best practice for managing Rate Matrix?

     

    Should we create new Rate Matrix line entry even if there is no change in the existing rate matrix (Rate or Class)?  For example:  Contractor "A" has the start date of 1/1/2017 and finish date of 12/31/2017 with the rate of $20.  

     

    Option#1:  Extend the finish date to 12/31/2018

    Option#2: Create new rate matrix record for the period 1/1/2018 to 12/31/2018 and keep the same rate.

     

    What is the best practice?

     

    I have few other questions:

     

    1. Is there any impact, if a resource is deactivated but the rate matrix is entered for future dates?
    2. Should we update the Rate 'finish date' to the resource 'termination date' when the contract is terminated?

     

    Thanks

    -Venkitta



  • 2.  Re: Rate Matrix - Industry Best Practice

    Broadcom Employee
    Posted Dec 26, 2017 04:00 AM

    Hi Venkitta,

     

    Official documentation on this topics, hope this will help you answer the questions you have 

     

    Set Up a Financial Cost and Rate Matrix - CA PPM - 14.2 - CA Technologies Documentation 

     

    Technical Document - CA PPM: How should the rate matrix be configured? 

     

    Regards

    Suman Pramanik 



  • 3.  Re: Rate Matrix - Industry Best Practice

    Posted Dec 26, 2017 07:44 AM

    Thanks Suman for sharing the documentation links. 

     

    Actually, I would like to hear from other people who work for various customers and share their experience/recommendations.

     

    Thanks

    -Venkitta 



  • 4.  Re: Rate Matrix - Industry Best Practice

    Posted Dec 27, 2017 09:29 AM

    Hi Venkitta, 

     

    I am trying to provide you suggestion accordingly: 

     

    Should we create new Rate Matrix line entry even if there is no change in the existing rate matrix (Rate or Class)?  For example:  Contractor "A" has the start date of 1/1/2017 and finish date of 12/31/2017 with the rate of $20.  

    Option#1:  Extend the finish date to 12/31/2018

    Option#2: Create new rate matrix record for the period 1/1/2018 to 12/31/2018 and keep the same rate.

     

    Both the ways are fine. But it depends on how you usually maintain all the rates in your organization. If you want to have rates for individual years then go with option 2. One good thing of this is all your rates will be based on the calendar/fiscal years. And a disadvantage would be that you will be having more number of rows unnecessary.

    So if you want to track rates only based on the value of rates or only track the changes then you can use the existing row and extend the finish date that is follow option 1. 

     

    Thanks,

    Abhisek Dhar



  • 5.  Re: Rate Matrix - Industry Best Practice

    Posted Dec 27, 2017 09:30 AM

    Hi Venkitta, 

     

    Your other questions: 

    Ques 1. Is there any impact, if a resource is deactivated but the rate matrix is entered for future dates?

    Answer: No, I don't think that there will be any negative impacts because once the resource will cross its termination date, he will not be able to report time in the PPM, I believe.  

    Ques 2. Should we update the Rate 'finish date' to the resource 'termination date' when the contract is terminated?

    Answer: Not needed. But by this question, I wonder if you are having individual rates for individual resources. You can do that for few resources, but if you are doing that for all the resources then it is not at all a good practice. You will create load on the Rate Matrix. Try to assign rates based on the departments, resource class, roles etc. to optimize the rate matrix definitions. 

     

    Thanks,

    Abhisek Dhar



  • 6.  Re: Rate Matrix - Industry Best Practice
    Best Answer

    Posted Dec 28, 2017 03:51 PM

    Hi Venkita,

    Based on the limited information available in the scenario that you have shared and assuming that the resource's information can only be derived from the row in question, I would recommend option #1. When it comes to Rate Matrix, you want to keep it as simple as possible. The lesser the number of rows, the better it is. 

     

    Re: your questions: 

    1. Is there any impact, if a resource is deactivated but the rate matrix is entered for future dates?

       Could you please elaborate on the kind of impacts you are concerned about? Let me try and answer some questions    that could arise:

          1) From a Financial Planning standpoint the Inactive resources will be accounted for when updating a cost plan.             Here is an article that talks about how inactive resources are treated when populating a cost plan - CA Clarity Tuesday Tip: How Do Inactive Resources Affect Cost Plan Populate 

          2) Inactive resources cannot be used for posting actual costs. A lot of customers have to account for this when their          resource deactivation may not be aligned with their cost/time processing. 

          3) The use of Termination date will require a different post to explain  However, for your benefit, the termination          date affects the ability to enter time, availability of the resource and a resource's allocation to a project. Here is a             thread that may help - CA Clarity Tuesday Tip - Hire Date, Termination Date – What they do! 

          4) To your specific question on whether the "Termination Date" should be aligned with the "To" date in the rate          matrix - No need to do that at all. You just need to take into account #1,  #2 and #3 as part of your routine          operations for handling resource turnover. 

     

    Hope the explanation helps. 

     

    Thanks,

     

    Regards,

     

    Debroop



  • 7.  Re: Rate Matrix - Industry Best Practice

    Posted Dec 29, 2017 03:21 AM

    Thanks Debroop for the detailed response.  



  • 8.  Re: Rate Matrix - Industry Best Practice

    Posted Dec 29, 2017 03:42 AM

    Should we clean up rate matrix for the terminated contractors or leave as it is?  When I run the Rate matrix job, does it include inactive resources also or only active resources?



  • 9.  Re: Rate Matrix - Industry Best Practice

    Posted Jan 04, 2018 11:36 PM

    I have not seen terminated contractors being removed from rate cards. Plus there could be implications to doing that. Not sure about the Rate Matrix job.