AnsweredAssumed Answered

Resource Constraints in Automatically create project Schedule

Question asked by CiraFalabella on Dec 28, 2017
Latest reply on Jan 22, 2018 by CiraFalabella

Hi,

I was trying to change de default value for Resource Constraints to 'Cleared'  but I couldn´t do that.  Somebody know how can I do that.

 

Thanks a lot,

 

Cira

Automatically Create Project Schedules with Autoschedule

 

Resource Constraints
Specifies if you want Autoschedule to consider resource availability when scheduling the project.
Default: Selected

Note: If you clear the check box, Autoschedule treats resources as if they have unlimited availability. Each task is scheduled against the total availability for the resource, but not against the remaining availability for the resource which takes other task assignments into consideration. This results in the shortest possible schedule, but it can also cause over-commitment of resources.

Outcomes