AnsweredAssumed Answered

Rate Increase not updating the cost plan

Question asked by vs00500773 on Dec 29, 2017
Latest reply on Jan 1, 2018 by vs00500773

CA-PPM Version 14.3.0.298 02 6

 

Here are the steps to reproduce:

 

  1. Create a contractor resource and enable 'Financially Active'
  2. Create a Rate Matrix and enter $100 for 'Rate', 'Standard Cost', 'Actual Cost' fields
  3. Run the 'Rate Matrix Job'
  4. Create a cost plan using 'Populate from Task Assignments'. The ETC*Rate will be populated
  5. Go to Rate matrix and increase the Rate by 10%
  6. Click on 'Preview'
  7. Select the checkbox for the contractor row and submit
  8. I get the message 'Row already exists' but the cost plan is not updated with the increased rate

 

Am I missing something?

 

 

 

Thans

-Venkitta

Outcomes