  • 1.  Rate Increase not updating the cost plan

    Posted Dec 29, 2017 03:34 AM

    CA-PPM Version 14.3.0.298 02 6

     

    Here are the steps to reproduce:

     

    1. Create a contractor resource and enable 'Financially Active'
    2. Create a Rate Matrix and enter $100 for 'Rate', 'Standard Cost', 'Actual Cost' fields
    3. Run the 'Rate Matrix Job'
    4. Create a cost plan using 'Populate from Task Assignments'. The ETC*Rate will be populated
    5. Go to Rate matrix and increase the Rate by 10%
    6. Click on 'Preview'
    7. Select the checkbox for the contractor row and submit
    8. I get the message 'Row already exists' but the cost plan is not updated with the increased rate

     

    Am I missing something?

     

     

     

    Thans

    -Venkitta



  • 2.  Re: Rate Increase not updating the cost plan

    Posted Dec 29, 2017 03:51 AM

    rate dates overlap existing, adjust previous row first

     

    but the cost plan is not updated with the increased rate

    because it's not in the matrix yet 



  • 3.  Re: Rate Increase not updating the cost plan

    Posted Jan 01, 2018 03:02 AM

    Hi Andrew

    Thanks for the response.  Here is how, I set the date and I get 'No results found'

     

    Source Date From : 12/1/17

    Source Date To : 12/31/17

    New Date From : 1/1/18

    New Date To: 2/28/18

     

     

    The bottom line is, I want to increase the Rate by 10% for a specific contractor.