Rally Software

  • 1.  Why do I only see one Initiative in my Portfolio Timeline?

    Posted Jan 23, 2018 10:34 AM

    I have several Initiatives in my workspace but only the first one is displayed in the Portfolio Timeline.  Why?



  • 2.  Re: Why do I only see one Initiative in my Portfolio Timeline?

    Posted Jan 23, 2018 01:19 PM

    You made me curious so i checked it on my end.  It appears the only Initiatives that appear are the ones that have a Planned Start Date, Planned End Date, State, and possibly Preliminary Estimate.

     

    Do the Initiatives that show up have a value for these fields and the others do not?

    PlannedEndDate

    PlannedStartDate

    State

    PreliminaryEstimate



  • 3.  Re: Why do I only see one Initiative in my Portfolio Timeline?

    Posted Jan 25, 2018 08:55 AM

    In order for a portfolio item (in this case initiative) to show on your portfolio timeline, the Planned Start Date and Planned End Dates must be filled in.