AnsweredAssumed Answered

Differents ranges for the Color Stoplights

Question asked by CiraFalabella on Jan 24, 2018
Latest reply on Feb 6, 2018 by Abhisek

Hi,

 

I want to know how can I do to configure Stopligths for projects with different values that mention in documentation 

 

This is an exampl for % Schedule

Stoplights:

  • Green. The investment is ahead of schedule or on schedule.
  • Yellow. The investment is between one and ten percent late.
  • Red. The investment is more than ten percent late.
  • White. The schedule percentage is undefined.

 

I need to change  to:

  • Green. The investment is  is between one and five percent late.
  • Yellow. The investment is between six and ten percent late.
  • Red. The investment is more than ten percent late.
  • Black.  The investment is more than  ten percent late.
  • White. The schedule percentage is undefined.

 

Thanks in advance,

 

Cira

Outcomes