Clarity

  • 1.  Error in dates late

    Posted Feb 05, 2018 03:07 PM
      |   view attached

    Hi, 

    I have an issue with dates late indicator because in the project I see 14 days late,  but all of project tasks have cero dates late . I can't figure out that situation. Or there are other task type that maybe impact in that indicator?

     

    Thank you so much,

     

    Cira



  • 2.  Re: Error in dates late
    Best Answer

    Posted Feb 05, 2018 11:30 PM

    Firstly, I am unable to view or download the screenshot that you have attached in the question, so I am going by certain assumptions as per my experience. I think you project is showing late because the project finished after the baseline finish date. The tasks might have 0 ETC before the finish date but that does not mean the project is running on schedule. May be the tasks were extended after taking the last snapshot of the project. So even if they got over by that extra time, the project still crossed the date that was taken in the last baseline. Hence, it will show the project as delayed. Hope that helps. 

     

    Thanks,

    Abhisek Dhar



  • 3.  Re: Error in dates late

    Posted Feb 06, 2018 04:07 AM


  • 4.  Re: Error in dates late

    Posted Feb 06, 2018 09:36 AM

    Thank you for Docs. It will help me with my users.



  • 5.  Re: Error in dates late

    Posted Feb 06, 2018 09:34 AM

    You are right, than you Abhisek