Clarity

  • 1.  Newbie: PMs approving team member's time entries question.

    Posted Feb 08, 2018 10:40 AM

    Hi, Is it possible to have PMs approve timesheet entries entered in CAPPM for the project they manage when a resource may be on multiple projects and the resource is owned by a different people manager?  That is, each PM approve their own Project time.

     

    Secondly, assuming the above question is possible.... how difficult is it to set this up from a CAPPM administration perspective?


    Thanks in advance.

    Neil.



  • 2.  Re: Newbie: PMs approving team member's time entries question.

    Posted Feb 08, 2018 11:50 AM

    What you describe sounds like the out-of-the-box "Project Manager Approval" process. This is facilitated by action-items rather than by the (Resource Manager) access-rights method.

     

    If you search for "timesheet approval" on these boards you should find many discussions around the various merits of the different approval methods.