AnsweredAssumed Answered

Want to change the Task finish date

Question asked by muthukumaran.mohanarengan on Mar 23, 2018

I want to change the task finish date to 29-Mar-2018 for the following 2 tasks

 

A task

B task

 

If I want to change the task finish date as 29-Mar-2018 for "A task"  date is not updated . Its changed to 04/03/2018.

Similarly for B task also having same problem.

 

FYI Project Finish Date: 04/03/2018

 

can you please advice how I need to update task finish date to 29-Mar-2018 for those two tasks.

 

 

 

 

Outcomes