AnsweredAssumed Answered

Work Shifts and Tasks Start/Finish Dates

Question asked by juanv on Mar 29, 2018
Latest reply on Jun 18, 2018 by juanv

We are exploring the impact of Work Shifts in the integration with MSP. 

We changed the wortk shifts of 5 days of the Standard Calendar (Novembre 6th to 10th).

 

The default shifts are:

8:00 - 12:00

13:00 - 17:00

 

The new shifts for those dates are:

8:00 - 12:00

13:00 - 19:00  (2 aditional hours)

 

Ran the Time Slicing job, and then created new tasks "before" those dates, "within" those dates, and "after" those dates. However, the 3 tasks have the same hour in the Start Date and Finish Date fields.All of them are starting at 8:00 and finishing at 17:00 hrs. 

The Work Shift didint change anything.

 

The tasks hs no resources.

Any ideas wether this is an expected resutl or a bug ?

Outcomes