I have set all tasks to Fixed duration and have the max-load % checked off. Tasks are opened for time-entry only when Start Date is coming up. Despite this, either the task does not show up on the resource's timesheet in PPM, or if the resource books time a day before or after the Start/Finish dates, the duration changes. If there is ETC (in PPM) remaining on the tasks, then the duration changes too.