I have three Workflows (A & B & C). A is a "Master Workflow" that contains B & C.  (A is the Nightly Batch Workflow).

Workflow C has to wait for Task #7 of Workflow B to complete. Is there some way to do a dependency for that?

I'm debating on splitting Workflow B into 2 parts (B1 & B2), where C has B1 as a dependency, but for several reasons, I'd really prefer not to do that. 

So, what I am really wanting is Workflow C to have a dependency on Workflow B.Task7

Any ideas of how I might accomplish that?