Hello,

How do you configure an object to execute at the times below:

    Mon to Fri: 08:00 - 18:00  (every hour)
    Sat to Sun: 14:00  (once each day)

I have created a calender object with 2 weekly keywords MON_TO_FRI and SAT_SUN and an event object which calls my JOBP (workflow).

I can see several places to set the job start-time but not the to configure hourly run during the week and single run at the weekend.

Am not clear on where/how to configure the time that I wish the job to run.

Can anyone help?

Regards,

Howard.