Kranthisri_Kaja_7981

Issue with Internal and External Dependency in AE

Discussion created by Kranthisri_Kaja_7981 on May 17, 2016

We have scheduled SAP Jobs using AE scheduler and set dependencies within the AE workflows expecting the SAP Jobs to be triggered as per dependency. Unfortunately the internal dependency withing a Workflow is working expected as per AE ( seeing the statistics of the Job ) but not expected as per SAP scheduling. On further analysis we noticed that the RA Job in AE is only starting the SAP Job and is not waiting untill the SAP Job  is Complete hence the dependent job is being triggered.

Did someone ever run into this type of issue, if so please help us to fix this.


Regards,

Kranthi

Outcomes