How to set up External Dependency - the basics

Discussion created by Harriet_Kim_1764 on Jun 14, 2016
In this example, the external dependency is set to only run on the 4th of July.

1. Always set the expected status to ANY_OK in the 'External dependency' tab rather than in the task's dependencies tab.

Note: ANY_OK covers the following statuses = Ended inactive, Ended skip because of calendar, Ended OK

dfenfgdu6ybg.jpg

2. This external dependency will only run on the 4th of July.  Any other day, it will be skipped:

fafbunzd6grw.jpg

3. Leave the status blank in the task's 'Dependencies' tab.

yhi2g79a26sw.jpg