KumarRahul605332

Execute Once option issues

Discussion created by KumarRahul605332 on Aug 22, 2017
Latest reply on Aug 24, 2017 by Mike_Halliday_7686

Hi there!

We are currently using v9 AE and recently faced an issue while executing a job plan with the option execute once. I choose the option Execute Once with logical date and choose the date two days ahead however the job plan executed immediately.

I came across the below article and was able to replicate the issue.

Execute once" with "Use logical date" not resolving correctly in AE v10

So does this issue impact version 9 as well?

Thanks,

Kumar


Outcomes