IanGoddard606749

Process ignoring external dependency

Discussion created by IanGoddard606749 on Dec 11, 2017
Latest reply on Dec 11, 2017 by Pete Wirfs

We have a process which is on a calendar to make it run at 3.30 everyday.  The process has external dependencies which are on a calendar to only run at 3.30 on the last day of the month.  So the 1st process ignores these external dependencies everyday, which is fine.  However on the last day of the month, instead of it waiting for the external dependencies to run, it is also ignoring them on this day?  Any ideas why this is?

The properties of the external dependencies is set as 'only valid, when activated on the same logical date', else Wait.

Outcomes