How can I create processes for different OBS resources?

Question asked by Saulex on May 17, 2018
Latest reply on May 17, 2018 by urmas

Hello Everybody!

 

Currently in my organization we are trying to upload other areas to PPM whose processes 

are related to currently registered projects, so I think the best option is to keep them
in the same partition? (correct me if I'm wrong).

 

I have thought of an OBS structure on the areas in the following way:

 

 

 After making this structure, I started assigning resources to the OBS I generated.

 

 

In order not to impact with the processes that are currently in Clarity, I thought about creating processes that are initialized in automatic according to the OBS of the resource, however I do not find the solution.

 

For which I would like to know if it is feasible what I'm thinking about making this distribution in PPM and how you can customize the processes according to the resource that activates it. Otherwise, please, I would appreciate it if you can suggest the most appropriate way to deal with this issue.

 

Consideration:

-All areas send to eachother task and projects.

 

I was seeing that the use of partitions is completely independent one view of another so I did not see it as viable or if it can?

 

I hope your great support with my doubt

 

Thank you,