We are currently implementing CA PPM and have an issue around the rate matrix.
We are planning on have a rate matrix for contractors and permanents which can be used for project budgetting purposes but when the project is approved we would like to update the contractors rates to their actual rates.
Is there a way to do this that still enables us to get resource demand and forecasting and not maintain individual rates in the rate matrix for each contractor? We have been advised that we can put the actuals for the contractor in the cost plans, but then we don't get the resource demand and forecasting.
How has everyone else managed to get around this issue?