CA-PPM 14.2
I have a contractor who is playing both Developer and Architect role and I have entered the Rate Matrix for two different rates.
A resource can be mapped to only one role at the resource level but whereas I can assign different role at the project level.
On the Rate matrix property, I have added Resource Role and entered the rate.
The resource enters timesheet tasks for both (developer and architect)
Does the rate matrix pick up the role from Investment role or resource primary role page?
Example:
1/1/2018 - 12/31/2018 - Developer - $75
1/1/2018 - 12/31/2018 - Architect - $100
Project A - Developer
Project B - Architect.
Thanks in advance for your help