Question asked by JayaSantoshKumar on Aug 2, 2018
Latest reply on Aug 2, 2018 by Abhisek

If a resource has 40 hrs allocation each week , then Allocation column in Team --> Detail is showing 160 for 4 weeks.

 

When i go to configure --> List column section -->  fields --> Allocation-properties and choose the Percentage option with decimal as 2 , as per below screenshot, then the Allocation column shows me 160.00% .

 

Correct me if i am wrong , or Is there any other column to get the Allocation % ?

 

When i see the OOTB portlet under Resource planning then it shows 100% under Allocation % column and 160 under Allocation.

 