AnsweredAssumed Answered

Different Project Start date for different Users in Advance reporting

Question asked by harikumar on Aug 27, 2018
Latest reply on Aug 29, 2018 by harikumar

Hi All,

 

We have created a Jasper report which shows Project Details. Also we  took one project(Project A) for testing. The Project Start date was on 2nd Jan 2018.

 

To different users Res1 and Res2 with two different time zone (for eg: Res1 CST and Res2 EST) ran the same report for same project(Project A). Then the report shown different Start date for these two resources.

 

For Res1, report shown 1st Jan 2018 and for the Res2, the report shown the correct Start date ie; 2nd Jan 2018.

 

Can someone help me to fix this.

 

Thanks

Hari

Outcomes