AnsweredAssumed Answered

Other Work for Non-Project Work?

Question asked by GrantL01 on Aug 27, 2018
Latest reply on Aug 28, 2018 by Christopher Yardin

Our company uses CA PPM, currently they keep all non-project work: vacation time, departmental support meetings, service requests, training etc. are all done as projects.  They are looking to start using resource planning and want to continue to use projects for the above items.  Should those items be classified as other work instead?  Also, if so, are they reportable in CA PPM?  Any suggestions/advice for setting up "other work" would be greatly appreciated.

 

I'd rather have the system setup correctly, instead of incorrectly if possible.

 

Thank you!

Outcomes