  • 1.  % Complete Change in middle of the project

    Posted Sep 13, 2018 03:47 AM

    Can we change the % complete calculation from Manual to Efforts or wise versa  during the project execution phase? We already have lot of actual posted on these projects. Is it ok to change the %complete. Thanks in advance



  • 2.  Re: % Complete Change in middle of the project
    Best Answer

    Broadcom Employee
    Posted Sep 13, 2018 09:18 AM

    It can cause issues if you change it, so it's not supported to change it in a project unfortunately. 

    See: Create Projects, Teams, and Tasks - CA PPM - 15.4.1 - CA Technologies Documentation for more details. 

    However, I know at times customers may accidentally set the wrong % Complete Calculation method and have to change it (Example the % Complete Calculation Method that is supported with MSP is Manual so if a customer is using a different method it causes issues). In those types of circumstances, I'd recommend testing it out in non production to measure the impact to the data in projects to make sure it doesn't cause any negative side effects and be aware it would be at your own risk if you do hit a data issue. An example of an issue I found reported is when a project was set to manual to update the % Complete for tasks without assignments. When the customer switched the % Complete calculation to Effort, the customer then lost lose those updates to those tasks. 



  • 3.  Re: % Complete Change in middle of the project

    Posted Sep 16, 2018 02:40 AM

    Thank you Kristin