  • 1.  Finish dates in clarity is one day behind the start dates

    Posted Sep 20, 2018 08:48 AM

    The finish dates in task tab in clarity is one day behind the start date. For example if the start date is 20/09/2018 then the finish date is 19/09/2018.(the particular task is a milestone) But when we download the tasks to mpp the dates are correct.  Any suggestions? Please help.



  • 2.  Re: Finish dates in clarity is one day behind the start dates

    Posted Sep 21, 2018 11:42 AM

    How does the prfinish and prstart fields look in the db?

    Start und Finish should be the same for milestones (finish counts).

    Probably some sort of a midnight date  related issue. Start = Finish but as midnight date.

    Check for example the following kb article:  

    On my report, the Finish Date is showing one day l - CA Knowledge