Does anyone know if the AC/CAPPM integration creates CAPPM Tasks from ALL AC Features, or only from those that are not in a "Completed" state? And if so, what is the definition of "Completed"? Is it Agile State = Completed, or a non-null Agile Actual Finish date on the Feature, or something else?
Asking because we're considering establishing integration between a very old AC Initiative and a very old CAPPM project. The AC Initiative has a LOT of old, completed features and we're wondering if the integration will create a lot of unnecessary Tasks in CAPPM.
Any info anyone has on this will be much appreciated. Thanks!
Alan Brobst
GE Transportation Digital Solutions
+1 (816) 600-1116
Hi Alan, the Agile Central/PPM integration syncs all Features in your PPM Project regardless of the Feature state, age, or date of the Feature.