Does anyone know if the AC/CAPPM integration creates CAPPM Tasks from ALL AC Features, or only from those that are not in a "Completed" state?  And if so, what is the definition of "Completed"?  Is it Agile State = Completed, or a non-null Agile Actual Finish date on the Feature, or something else?

 

Asking because we're considering establishing integration between a very old AC Initiative and a very old CAPPM project.  The AC Initiative has a LOT of old, completed features and we're wondering if the integration will create a lot of unnecessary Tasks in CAPPM.

 

Any info anyone has on this will be much appreciated.  Thanks!

 