  • 1.  CA PPM integration with MS Project

    Posted Nov 06, 2018 04:21 PM
      |   view attached

    #msprojectconnector #msproject

     

    Hi,

     

    We have some problems using Ms Project with CA PPM integration because the dates can moves in some cases  and cause inconsistence between plans in project and CAPPM.

     

    I attach one simple example to show the problem.

     

    I read this discussion 

    Does anyone use MS-PROJECT and CA on day to day baisis

    Pregunta realizada por pgalipeau el 01-jun-2018
    Última respuesta el 01-jun-2018 de Kristin Schroer

    and want to know if is possible some answer in order to solve that issue. 

    Attachment(s)

    docx
    MSProject Issue Example.docx   528 KB 1 version


  • 2.  Re: CA PPM integration with MS Project

    Broadcom Employee
    Posted Nov 08, 2018 12:49 PM

    Hi Cira,

     

    What version of CA PPM are you using? Which MSP Interface (Legacy or XML) are you using? What version of MSP are you using?

     

    All of those matter, as differences exist in versions.



  • 3.  Re: CA PPM integration with MS Project

    Posted Nov 13, 2018 07:54 AM

    Thank you Janet,

    My answers

    What version of CA PPM are you using? 15.3.0.200

    Which MSP Interface (Legacy or XML) are you using? XML (64 bit)

    What version of MSP are you using? 16.0.9126.2295 (64 bit)

     

    Please let me know if you need something else

    Regards,

     

    Cira



  • 4.  Re: CA PPM integration with MS Project

    Posted Nov 22, 2018 05:28 PM

    CiraFalabella - I have had similar situation recently while working with schedule updates from MSP to CA PPM. I have identified Task Calendar was creating an issue in my case. Base Calendar set in PPM excludes holidays while MSP's Task Calendar when set as '24 hours' it gives up different date to what is there in Clarity.

     

    Scenario was like we had project cut over dates over weekend, which was correctly showing up in MSP and when saved back to PPM, we had no issues. However, when we exported the same schedule again and updated %complete for few other tasks, and did not update the dates/task calendar settings in MSP for cut over tasks and saved the schedule back to CA PPM dates were getting changed. The reason for this was we don't have an option to save Task Calendar mapping to Clarity. I have raised a support case to CA to check how these task level calendar settings can be handled.

     

    Similar to above scenario please check if this is something to do with task calendar in your case. If you have made any progress in resolving this, please share the solution.

     

    Thanks,

    Praneeth



  • 5.  Re: CA PPM integration with MS Project

    Posted Jan 14, 2019 10:19 AM

    Thanks Praneeth,

     

    Regards,

     

    Cira