We have CAPPM integrated with Agile Central. I can see data from Agile Central when I change my project dashboard to Agile. However, the tasks do not show the % complete.
Hi,
% Complete does not seem to be one of the attributes that gets updated from Agile Central. The attributes mapping list here: CA PPM and CA Agile Central Attribute Mapping - CA PPM - 15.5 - CA Technologies Documentation .