Release Automation

  • 1.  We are planning to move Lisa DB

    Posted Nov 29, 2018 07:13 AM

    We are planning to move Lisa DB, Lisa databases from one data-center to another data-center.

    Please suggest us the required below steps for post DB migration completed.

    1. Verification steps
    2. Publish the Zero deployment plan



  • 2.  Re: We are planning to move Lisa DB

    Broadcom Employee
    Posted Nov 29, 2018 12:12 PM

    Hi Ikano,

     

    Please provide the DB details. 

     

    If you need to move the DB from one datacenter to another please make sure that the DB name in the new datacenter remains the same and Nolio - database.properties is updated with the machine name(This is the scenario for SQL Server)

     

    You can move the entire DB dump from DB(Datacenter1) to DB(Datacenter2).

     

    Regards,

    Sachin