  • 1.  Where do you key in your Project Budget in CA PPM 15.5

    Posted Dec 03, 2018 01:31 PM

    I am wondering where in CA PPM 15.5 do you key in your budget. In the documentation it states go into the properties of you project and from the properties menu select Budget. The budget option does not exist in my CA PPM 15.5 version. We are new to the financial module and CA PPM 15.5. Any help you can provide will be greatly Appreciated.



  • 2.  Re: Where do you key in your Project Budget in CA PPM 15.5

    Posted Dec 03, 2018 05:24 PM

    Hi chrisflynn,

     

    Budget can be keyed in different ways:

     

    1. Project Properties -> Financial Summary -> Financial Plan Summary (Section)  

    Above option is only editable if there are no cost plans created for that project.

     

    2. Project -> Financial Plans - > Cost Plans

    Cost plans are used to create detailed financial plans for a specific period of time of the project, by grouping by financial attributes like cost type, transaction class etc. Cost plans can be revised and can mark latest financial cost plan as plan of record and that cost plan can be used to create a budget plan to reflect the approved budget for the project.

     

    More details on how to create cost plans/benefit plans/budget plans are here: https://docops.ca.com/ca-ppm/15-5-1/en/using/getting-started-with-classic-ca-ppm/financial-management/create-detailed-financial-plans#CreateDetailedFinancialPlans-PrerequisitesforCreatingDetailedFinancialPlans

     

    Regards,

    Praneeth