I have a scenario like most of the project PMs have, where project go live/cut over dates are on weekends. When I try to set that in project schedule, task dates are changing because of the base calendar settings. To my knowledge, I don't think we can have Project/Task Calendar in Clarity. Correct me if I am wrong! If my statement is correct, what is the suggested alternative in this scenario to apply non-workdays for those kind of cutover date, other than specifying constraints?
I was also looking for alternative solutions in communities and I was unable to unable to use links in this post:
https://communities.ca.com/thread/2290242
Note: We are using MSP integration.
Impact: MSP Integration is changing task start/finish dates as there is no way of setting task calendar at project or task level.