Hi there, we have a client whos asking if its possible to make the (Average Allocation %) on the team, on project, a default by 0.

 

So every time you add resources, instead of 100%, is 0%.

 

Is that in any way possible, I dont imagine, but, sometimes ppm surprise me.

 

Cheers,

Pablo