We have been using CA PPM for project management for the last year including using timesheets to capture time. However, at that time we did not apply a cost rate matrix. We have now done so which has worked and we are seeing the costs of actuals tick up. However, our actual costs do not include all the timesheets posted prior to us implementing the cost rate matrix.
Is there a way to unpost the timesheets in bulk and repost them with the rate now implemented in our cost rate matrix without creating the need for reapprovals etc.? We will also have had resource leave the business in that period which could impact. Without being able to do this our actuals on long running projects are clearly too low.
This is probably a fairly common requirement but I have yet to find a solution.