Hello,

I am writing a report in SSRS that pulls data from Clarity's tables. I need to see:

1) Actuals
2) ETC
3) Pending Actuals

At the TASK level. So a resource is assigned to a project, and then has tasks. I want to list each resource's task in that project and the number of hours listed above.

All works just great until I get to pending actuals. I have time slices setup for the actuals and ETC on a daily basis (the report is date driven TO / FROM). When I time slice on "time sheets" I don't get any hours at the task level. Does anyone here know how to setup the slicer job to slice pending actuals at the task level?

Any help would be greatly appreciated!

Thank you

Justin