Accept Hard Allocation button on Resource > Allocation tab

Question asked by navzjoshi00 Champion on Aug 18, 2011
Latest reply on Aug 22, 2011 by navzjoshi00
The below mentioned scenarios have been carried out using admin login -

The resource that needs to be hard-booked is in mixed booked state

Scenario 1
1. Access Project (P) > Team tab
2. Tick the checkbox against a resource (A), and click Accept Hard Allocation
Result:- The resource is Hard Booked


Scenario 2
1. Access Resource (A) > Allocation tab
2. Tick the checkbox against a project (P), and click Accept Hard Allocation
Result:- The resource is not Hard Booked, and is still Mixed Book - Why ?