Hi

We have large projects in Clarity with each project having ~1500 tasks and ~7000-8000 assignments and growing. Project Managers using MSP 2003 can open their large project in MSP in less than 2 minutes but it takes 20-25 minutes for managers who manage them in MSP 2007.

Is there any setting that I have to do in either Clarity or MSP 2007 so that the performance is similar ?

I followed all standard settings in MSP and best practises as per green papers but is of very little help

Please advise

Thanks
Siva