AnsweredAssumed Answered

MSP Copy Paste issue

Question asked by Dave.Burrows1.1 on Sep 29, 2011
Latest reply on Oct 4, 2011 by another_martink
I have been informed that if a user is using MSP for scheduling and they copy a row and past it into the schedule that this will copy internal references for Clarity, resulting in unpredictable results.
Has anyone experienced this?
How likely is it that corruption would occur?

As we are doing a review to see if moving to MSP from OWB would be a good move, I see this as a major concern. I have visions that it could corrupt my database.

As copy and paste are such commonly used functions I would also expect that this happens on a regular basis.

In the event that a user does this are there known fixes to resolve any issues.