AnsweredAssumed Answered

Microsoft Project Integration Problem

Question asked by Jim_Fuhring on Jun 30, 2010
Latest reply on Aug 3, 2010 by Michael
I have a new Vista system with MS Project installed. My old system, Windows 2000, had the Microsoft Clarity Integration package for MS Project working just fine. With the upgrade, when I attempt to install the interface, I get the following error message:

Error 1327: Invalid Drive H:\

The installation fails at that point. I can no longer access the WBS and task list in my project. What is the installer trying to do? Why is it trying to install the interface on H:\?

Thanks

Outcomes