ca.portal.admin

17.0 Upgrade

Discussion created by ca.portal.admin on Jan 28, 2010
Latest reply on Jan 28, 2010 by ca.portal.admin
How long is everyone taking to install 17.0? I'm talking about from the
day
you download it from CA to the day you are 100% running in production.
The
site I support is upgrading from 16.0 SP7 to 17.0 SP1.



Mark Grindstaff
"
IDMS 3rd-party providers forum
IDMSVENDOR-L@LISTSERV.IUASSN.COM
SMTP
IDMSVENDOR-L@LISTSERV.IUASSN.COM
IDMSVENDOR-L@LISTSERV.IUASSN.COM
SMTP








Normal

Normal
Re: 17.0 Upgrade
"This is the hi-level plan I gave my management.

They wanted me to go faster, but based on my 16.0 implementation
experience here, I demurred. VM is a special issue here. And we like to
let our internal customers have plenty of time to see the transparency
of the upgrade.

Yeah, there's some fluff, in there, but I don't need to explain to y'all
the rationale between Man_days and Calendar_Days, do I? . . . 8^D . . .
for some reason, it seemed to me that my management had no concept of
this, er, uh, concept . . . I'm almost ready for step6, but I'm going on
vacation next week. . . 8^) . . .We might very well install both
production CVs closer together too, but I'll cross that bridge when I
get to it.

IDMS 17.1 High-Level Install Plan

Step Man-Days Cal-Days Description
1 1.5 3.8 download software
2 5 12.5 Receive, Apply, & Accept base IDMS 17.1 install
on AEIS -- catchup Hyper APARs
3 5 12.5 3rd Party Software Install
(FAC,PREALERT,VEGA,SOL,EZ)
4 1 2.5 Base Software Verification
5 5 12.5 Retro-fit customizations
6 11 27.5 Application Environment Verification, including
VM interface
7 5 12.5 Utility Verification
8 5 12.5 New Feature Assimilation
9 5 12.5 DBA Sandbox CV Upgrade & testing
10 11 27.5 Developer Unit Test CV Upgrade & Testing
11 11 27.5 QA/UAT/Training CV(s) Upgrade & Testing
12 5 12.5 First Production CV Prep & Upgrade
13 5 12.5 Second Production CV Prep & Upgrade
75.5 188.8 Total Days
6.3 Total Months