Capacity for Consultants

Question asked by Tammi Champion on Aug 13, 2010
Latest reply on Aug 13, 2010 by Tammi
Hi Everyone,

How do you capture capacity for a consultants that is contracted to work for you from Sept to Dec, but they may only work 8 hours a day for two weeks in September and two week in October but you are not sure what weeks they are working. How do you reflect their capacity, is it still considered a full FTE for the whole month or is it 4 hours a day for two weeks? Should I just activated their account only when they are working so the system can reflect their true capacity? How does your organization use it?

Thanks
Tammi