Open workbench, help?

Question asked by pirjo on Dec 10, 2011
Latest reply on Dec 11, 2011 by another_martink
I am using open workbench, version 12.0.5.5350.

Have a large project, lasting over a year.

Need to follow actuals(cost, work days) vs scheduled (cost, work days).

Realized bcws doesn't give right figures. Assume it's related to the bac value.

Have baselined the project, total usage equals with the the project budget, but bac doesn't seem to update.

Read the open workbench help many times, didn't find explanations about the rules how values to different eva fields are calculated.
Assumed that bcws is based on the value of bac.

But what is bac based on?

And where are all the calculated fields explained. Properly.

Has anyone else faced the same problem? Found solution?