Resource Allocations

Question asked by timma.l.wilson on Dec 15, 2011
Latest reply on Dec 16, 2011 by timma.l.wilson
Open Clarity
Click on Resource Resource Planning
Click on Allocations Tab
Time Scale Value Settings:
Start Date = Start of Current Month
Time Scale = Month
Number of Periods = 6

Question:
Why do allocations that have ended still appear on this screen?
For instance, Allocation Start = 2/1/11, Allocation Finish = 10/10/11.
If the allocation ended in October, and I asked to see allocations for December through May, why do projects with a zero allocation in this time frame still appear on this page.