AnsweredAssumed Answered

Collecting Monthly Budget Information

Question asked by AndreaMcVey on Sep 20, 2010
Latest reply on Sep 22, 2010 by Michael
We are on version 12.0.6.5471.

The requirements call for the following information to be collected at the project level.
The numbers are entered and not calculated - this group is not doing time reporting and the costs are consolidated - not just labour.

Each month of the project, collect projected budget cost, actuals (if month is past).
Additionally, the information would ideally be captured historically (as opposed to overwriting data) so that comparisons can be made over time.

Is there a tidy way to capture this? I don't want it to be labourious, or the users will never accept it.
Any suggestions are welcome...
Everything I have come up with is decidedly inelegant.
Andrea

Outcomes