HELP!!!! Migrating MSP projects

Question asked by Joel on Jan 5, 2012
Latest reply on Jan 10, 2012 by Chris_Hackett
Has anyone ever migrated MS Project managed plans from one system to another, importing into a prod system in use?

From Clarity 12.0.05
To Clarity 12.0.1.06 Generic Fixpack 009
MSP 2007

Technical detail:
The issue that we are having is that the Project XOG does not move the MSP file BLOB stored in the PRDOCUMENT table.
This is because the MPP file stores the internal IDs of the clarity objects, these are invalid when moving to the new sytem.

Any help would be greatly appreciated.