AnsweredAssumed Answered

Allocations 'Weekly Detail' does not allow edit mode on ETC - why?

Question asked by matpj on Jan 16, 2012
Latest reply on Jan 16, 2012 by matpj
Hi all,

i'm playing around with the Resource Planning screens in Clarity and looking in particular at the 'Weekly Detail' portlet in the Allocations tab.
When the virtual column is set to 'Allocation', it allows editing.
If allocation is replaced with ETC, it does NOT allow editing.

Can anybody explain why that is?

Thanks in advance,
Matt

Outcomes