Hi,

We are sometimes experiencing an issue with the cost plan to budget mechanism, where a budget amount is not equal to the cost plan it originates from. We found out that one option is to submit and approve a zero budget, to remove any ghost entries, before submitting the revised cost plan.

Did you already experience such issue? Do you have any tricks you can share for dealing with this problem, as our current workaround add more complexity to the cost plan to budget validation process?

Regards

Brice