Resource Planning>Allocations>Weekly Details - Time Scale Values - ISSUES

  • 1.  Resource Planning>Allocations>Weekly Details - Time Scale Values - ISSUES

    Posted Feb 04, 2012 01:51 PM
    Hello,

    Is anyone using the Resource Planning> Allocations > Weekly Details Portlet successfully - in particular, with the Time Scale Values of "Weekly"?

    We are encountering an error message: "The time periods requested do not exist. Review the column"s Time Scale setting."

    We do not know which column is causing the issue...we know there is data...if we pick Monthly we get data....if we pick Weeks, and go up to 14 weeks we are okay but anything beyond that, for weekly, generates the error (and then no data is displayed).


  • 2.  RE: Resource Planning>Allocations>Weekly Details - Time Scale Values - ISSU

    Posted Feb 04, 2012 02:38 PM
    TEC439086 tells which periods exist and TEC491657 gives more details on when the data is displayed.

    Martti K.


  • 3.  RE: Resource Planning>Allocations>Weekly Details - Time Scale Values - ISSU

    Posted Feb 04, 2012 03:11 PM
    Sorry Marti...that's too technical for me :)
    could you explain from a Business User perspective..what the problem is?

    Many thanks,

    Donna


  • 4.  RE: Resource Planning>Allocations>Weekly Details - Time Scale Values - ISSU

    Posted Feb 04, 2012 03:25 PM
    The time periods used in that portlet are system periods which are not user configurable and you can't even see the definitions in the GUI. My understanding is that they are timeslices
    The first doc tells you how many periods forward and to the past you can see of each type.

    The second doc says that if you have one time period outside those ranges you will get the error.
    It suggests that you configure you view to display just one period and then you can move one period at a time to see where the error comes.

    You may have actual data in a time period which gives the error. The error comes because that period is not sliced.

    Hopefully that will help you.

    Martti K.


  • 5.  RE: Resource Planning>Allocations>Weekly Details - Time Scale Values - ISSU
    Best Answer

    Posted Feb 04, 2012 03:37 PM
    Thanks Marti...I will pass along the info to our tech support to see if the explanation helps :)

    Best regards,

    Donna


  • 6.  Re: [CA Clarity General Discussion] RE: Resource Planning>Allocations>Weekl

    Posted Feb 04, 2012 08:45 PM
    What version are you in? Thanks, Steve Steve Seaney +1 224 678 8198 From: CA Clarity Global User Community [CommunityAdmin@communities-mail.ca.com] Sent: 02/04/2012 08:37 PM GMT To: "mb.2277340.97475238@myca-email.ca.com" <mb.2277340.97475238@myca-email.ca.com> Subject: [CA Clarity General Discussion] RE: Resource Planning>Allocations>Weekly Details - Time Scale Values - ISSU Thanks Marti...I will pass along the info to our tech support to see if the explanation helps :) Best regards, Donna Posted by:donna.waugh -- CA Communities Message Boards 97477778 mb.2277340.97475238@myca-email.ca.com http://communities.ca.com ----------------------------------------- ****************************************************************** This message originated from the Internet. Its originator may or may not be who they claim to be and the information contained in the message and any attachments may or may not be accurate. ****************************************************************** ----------------------------------------- ****************************************************************** This E-mail is confidential. It may also be legally privileged. If you are not the addressee you may not copy, forward, disclose or use any part of it. If you have received this message in error, please delete it and all copies from your system and notify the sender immediately by return E-mail. Internet communications cannot be guaranteed to be timely, secure, error or virus-free. The sender does not accept liability for any errors or omissions. ****************************************************************** SAVE PAPER - THINK BEFORE YOU PRINT!


  • 7.  RE: Re: [CA Clarity General Discussion] RE: Resource Planning>Allocations>W

    Posted Feb 09, 2012 02:49 PM
    Sorry Steve and Martin,

    I did not check for additional information - we are on v8.1 we can get approx 14 weeks of information on the Weekly Allocations portlet...if we ask for a higher count of weeks the allocation gantt displays the weeks columns but there is no information inside and we get the warning to check the columns timeslice...

    Any ideas?

    Many thanks,

    Donna


  • 8.  RE: Re: [CA Clarity General Discussion] RE: Resource Planning>Allocations>W

    Posted Feb 09, 2012 04:27 PM
    Use the user configurable time slices, configure them as you need and create a custom portlet.

    Martti K.


  • 9.  RE: Re: [CA Clarity General Discussion] RE: Resource Planning>Allocations>W

    Posted Feb 11, 2012 01:44 PM
    Hello Martti,

    Our support staff are trying to understand but this seems a little daunting....This may be an unusual request but it is possible to set up a conference call with you to discuss how to approach a customized portlet?

    I can reach out offline if you are interested.

    Many thanks,

    Donna


  • 10.  RE: Re: [CA Clarity General Discussion] RE: Resource Planning>Allocations>W

    Posted Feb 11, 2012 04:13 PM
    Instead of having to fall back to custom portlets, wouldn't it be cool if this just worked out of the box for us all? Allowing us to set the scale as we need?

    If you think this would provide business value to your organization, please click here and promote the idea Allow Administrative control over time slice ranges on OOTB System Data Providers.


  • 11.  RE: Re: [CA Clarity General Discussion] RE: Resource Planning>Allocations>W

    Posted Feb 22, 2012 04:13 PM

    donna.waugh wrote:

    Sorry Steve and Martin,

    I did not check for additional information - we are on v8.1 we can get approx 14 weeks of information on the Weekly Allocations portlet...if we ask for a higher count of weeks the allocation gantt displays the weeks columns but there is no information inside and we get the warning to check the columns timeslice...

    Any ideas?

    Many thanks,

    Donna
    FYI if anyone was wondering, it is still an issue in R13. Just finished my upgrade and noticed today it is still there.


  • 12.  RE: Re: [CA Clarity General Discussion] RE: Resource Planning>Allocations>W

    Posted Mar 28, 2013 10:23 AM
    That is as designed so not very likely to go away.

    Martti K.


  • 13.  RE: Resource Planning>Allocations>Weekly Details - Time Scale Values - ISSU

    Posted Feb 05, 2012 04:15 PM
    Another crack at it.

    Martti K.




    .

    Attachment(s)



  • 14.  Re: Resource Planning>Allocations>Weekly Details - Time Scale Values - ISSUES

    Posted Aug 25, 2016 04:04 PM

    https://communities.ca.com/servlet/JiveServlet/download/97478696-1-46332/The%20time%20periods%20requested%20do%20not%20exist.JPG